Remoteness defence struck out in cladding claim

In Orchard Plaza Management Company Ltd v Balfour Beatty Regional Construction Limited [2022], the Technology and Construction Court was asked to rule upon the Defendant contractor’s argument that the losses claimed against it were too remote to be recoverable at […]

Read More

D&B contractor liable for the cost of replacing defective cladding in the TCC’s first substantive decision post the Grenfell tragedy

Judgment has very recently been handed down by HHJ Stephen Davies in Martlet Homes Limited v Mulalley & Co. Limited, the first substantive Judgment from the TCC on defective cladding since the Grenfell tragedy in 2017. In associated Court of […]

Read More

Government ditches the role of Building Safety Manager in latest shake-up of the Building Safety Bill

In a further change to the Building Safety Bill put forward following the Grenfell Tower tragedy in 2017, the Government has now scrapped the requirement to appoint a Building Safety Manager during the occupation phase of a construction project. Background […]

Read More

Government gives industry deadline of early March 2022 to agree to a plan of action to remediate unsafe cladding

Since the Grenfell Tower fire in 2017, the Government has taken a number of steps aimed at addressing the building safety and cladding crisis. Those steps have included provision for financial contributions to remedying unsafe cladding through the ACM cladding […]

Read More