Excluding Liability for Deliberate Breach – Is Special Wording Required?

In the recent case of Mott Macdonald Ltd v Trant Engineering Ltd [2021] EWHC 754 the TCC considered whether an exclusion clause required exceptional wording in order to exclude liability for fundamental, deliberate and wilful breaches. Background Trant Engineering Limited […]

Read More

The TCC consider the circumstances in which an independent Category 3 design checker may owe a duty of care to a main contractor

In the recent case of Multiplex Construction Europe Limited v (1) Bathgate Realisations Civil Engineering Limited (in administration) (2) BRM Construction LLC (3) Argo Global Syndicate 1200 the TCC considered the scope of a professional design checker’s duty of care […]

Read More

Introducing New Claims – An Unnecessary Risk?

In the recent case of Martlet Homes Ltd v Mulalley & Co. Ltd, the court considered two different methods via which a claimant can seek to introduce additional submissions and arguments into its claim against another party. Background Martlet Homes […]

Read More

Contract Interpretation and Repudiatory Breach

In the recent case of Optimus Build Ltd v Southall & McManus, the Technology and Construction Court (TCC) considered a dispute in which the contractor believed the contract was a fixed price contract and the employer believed it to be […]

Read More

Adjudication Enforcement – “Subject to Contract” and Determination by Agreement

In the recent case of Aqua Leisure International Limited v Benchmark Leisure Limited, the Technology & Construction Court (TCC) considered an application for summary judgment to enforce an adjudicator’s decision in circumstances where there was an alleged determination “by agreement” […]

Read More

The Brexit Trade Deal and its Impact on the Construction Industry

On 24 December 2020, the UK and the EU reached a trade and co-operation agreement (the “Trade Deal”) addressing the arrangements that now apply between them. This bulletin highlights a number of the key elements of the Trade Deal which […]

Read More

Guidance from the TCC – No Final Account Provisions in the Contract?

In the case of JSM Construction Limited v Western Power Distribution (West Midlands) Plc, the Technology and Construction Court (TCC) considered whether the absence of a final account provision rendered a contractual payment mechanism inadequate. Background Western Power Distribution (West […]

Read More

Adjudication Enforcement – Guidance on Natural Justice and Jurisdiction

In the case of Global Switch Estates 1 Limited -v- Sudlows Limited, the Technology and Construction Court (“TCC”) dismissed an application for summary judgment to enforce an adjudicator’s decision due to material breaches of the rules of natural justice. Background […]

Read More

Letters of Intent and Incorporation of Standard Form Contracts

In the case of OD Developments v Oak Dry Lining Ltd, the TCC considered the operation and effect of a letter of intent (“LOI”) in the context of whether a JCT standard form sub-contract was incorporated. Background Oak Dry Lining […]

Read More

Payment Applications – The Devil’s in the Detail

In the recent case of RGB Plastering Ltd v TAWE Drylining and Plastering Ltd, the TCC considered an application by RGB Plastering Limited (“RGB”) for a declaration that an application for payment submitted by TAWE Drylining and Plastering Limited (“TAWE”) […]

Read More