
Earlier this year, the case of Grove Developments Ltd v Balfour Beatty Regional Construction Ltd attracted a lot of attention when it was held by the court that the contractor had no further entitlement to interim payment following expiry of […]
Read More
JCT has now published the Design and Build Contract 2016 and the Design and Build Sub-Contract 2016. In the second of our bulletins on these new editions, we take a look at more of the key changes that have been […]
Read More
JCT has now published the 2016 edition of the Design and Build Contract together with the Design and Build Sub-Contract Agreement and Conditions. There have been numerous changes to the wording of the contracts and in this first bulletin in […]
Read More
When the Late Payment of Commercial Debts (Interest) Act 1998 was amended by the Late Payment of Commercial Debts Regulations 2013, a new right to recover “the reasonable costs of recovering a debt” was introduced. Since then, there has been […]
Read More
JCT has now begun publishing the 2016 edition of its construction contracts in a phased roll-out, beginning with the Minor Works Building Contract (MW), the Minor Works Building Contract with contractor’s design (MWD) and the Minor Works Sub-Contract with sub-contractor’s […]
Read More
It is very common for contracts to contain a clause which provides that any variation to the terms of the contract must be agreed by the parties in writing. It is also very common for contracting parties to overlook these […]
Read More
Keeping detailed contemporaneous records of, among other things, the work carried out on site is critical for any contractor. Failure to do so can cause many problems, not least of which is the risk of not being paid. In the […]
Read More
Successfully incorporating standard terms and conditions into contracts can be a minefield and there is often considerable uncertainty about which party’s terms apply. Once the terms of the contract have been established, there is often the further question of whether […]
Read More
It is a well-established principle that only one dispute may be referred to an adjudicator in a single adjudication. However, a question which has not previously come before the courts is whether the same adjudicator may be appointed in two […]
Read More
It is a classic scenario; a schedule of interim payment dates is drawn up, but the works continue beyond the last date in the schedule – what is the remedy? The recent case of Grove Developments Ltd v Balfour Beatty […]
Read More