Can An Adjudicator Decide More Than One Dispute At The Same Time?

It is a well-established principle that only one dispute may be referred to an adjudicator in a single adjudication.  However, a question which has not previously come before the courts is whether the same adjudicator may be appointed in two […]

Read More

Payment Schedules – Run Out of Dates and You May Run Out of Payments!

It is a classic scenario; a schedule of interim payment dates is drawn up, but the works continue beyond the last date in the schedule – what is the remedy? The recent case of Grove Developments Ltd v Balfour Beatty […]

Read More

When is an Oral Construction Contract Formed?

2011 brought with it the long awaited amendments to the Housing Grants, Construction and Regeneration Act 1996. One of the most significant changes was that the definition of a “construction contract” was extended to include oral contracts, making it possible […]

Read More

Adjudication and Limitation Periods – You May Have Won The Battle, But Have You Won The War?

The Supreme Court recently made its first decision on adjudication in the case of Aspect Contracts (Asbestos) Ltd v Higgins Construction Plc. The Court considered what entitlement a party who has been ordered to pay money in an adjudication has […]

Read More

Applications for Payment – Get the Dates Right or Risk Losing Out!

It is quite common for the parties to construction contracts to depart from the payment dates set out in the contract for their own convenience or in the interests of helping each other out. However, this can have unintended consequences […]

Read More

A Payment Lifeline For Contractors and Employers Worth Taking Notice Of?

Last month we commented on the “give notice or pay on demand” legacy seemingly established in the case of ISG Construction Limited v Seevic College. This case took a pointed stance on the effect of the failure to serve a […]

Read More

Challenging Final Certificates Under JCT

JCT contracts include a “conclusive evidence” clause which provides that the Final Certificate constitutes conclusive evidence that all sums due to the Contractor have been accounted for unless proceedings challenging the content of the Final Certificate are commenced within 28 […]

Read More

Give Notice or Pay on Demand

In the recent case of ISG Construction Ltd v Seevic College the court had to consider whether an employer, who had failed to issue both a Payment and a Pay Less Notice, could ask an adjudicator to assess the value […]

Read More

Nominating Adjudicators: Don’t Abuse The Process!

The recent case of Eurocom Ltd v Siemens PLC has set alarm bells ringing within the construction industry, particularly with regard to the process of appointing an adjudicator. Background Siemens engaged Eurocom under a subcontract in April 2011 to install […]

Read More

Challenging a Final Certificate

When are adjudication proceedings deemed to commence? Many JCT contracts include a clause which provides that the final certificate constitutes conclusive evidence that all sums due to the Contractor have been paid unless proceedings challenging the content of the certificate […]

Read More